Pricing, and a little bit about estimation.

Filed under: agile, kanban, lean, scrum, Uncategorized — Tags: , , , , , , — Kurt Häusler @ 12:54

So I keep getting involved in discussions on twitter related to the different ways of basing prices for software projects, and it is hard to get some of the subtle details across in 140 character snippets so I thought it might be a good idea to put some ideas together in the longer form of a blog post. The whole thing is somewhat related to the #NoEstimates debate.

I also believe the base of my ideas is fairly mainstream. Most of the agile community (dominated by the Scrum community) talks about estimation in terms of estimating PBIs so you can plan how many to take on in each sprint. A few people still do it in ideal person days like Mike Cohn recommended back in the dark ages, which I am opposed to (but not to the point of getting into arguments about it) as I think there are some serious downsides to that approach. That is not a radical opinion, and it is the reason why most people use more abstract, relative units of size like story points, which I personally don’t advocate, but I don’t oppose either. Even most of the defenders of story point estimation for sprint planning recognise that the true advantage is in getting the team to talk about what needs to be done, and the actual estimate is a secondary benefit. A few of the more advanced teams, and even the inventor of story points Ron Jeffries himself, prefer to simply use a count of PBIs. This is the approach I find most sensible, when combined with backlog grooming and story splitting. Also after using Kanban for several years I have realised that estimating is pretty much wasteful. I don’t think that is a radical opinion either as it seems shared by much of the Kanban community, who make use of a metric called throughput which is essentially the same as velocity and is typically presented as a number of items done per unit of time.

But as long as all we are talking about is how many items to plan for each sprint, who cares? The consequences of over or underestimating are minimal. If we plan too few ask the PO for more, and the velocity goes up to plan more for the next sprint. If we over plan then we drop the velocity and plan less for the next sprint. As long as this is all we are using estimates for then who cares how we do it.

For me estimates are only really a problem when they are taken more seriously than intended. For example when calculating prices, or when forming an offer or contract that a customer may rightfully interpret to be a commitment to deliver, and expect to be based on something more solid than a guess. Sadly the agile community talks so much about estimation in conjunction with sprint planning, and very little about contracts and pricing. I have even heard people say that the way that contracts and prices are done is completely orthogonal to how the software “project” is carried out. I disagree completely. From my experience the way the contract is written and the way the work is priced are the fundamental factors that indicate to what degree any software development endeavour will be “agile” or not. Or should I say to what degree it is even appropriate for knowledge work and product development, or anything in the complex domain for that matter.

If some manager comes to the team and says “these requirements have to be done by the end of July, and we have a budget of 20 architect “person-days” and 60 developer person-days and 30 tester person days and 10 manager person days, now use Scrum to make it a reference agile project”, then your options are pretty limited.

I think the disagreements in the NoEstimates debate are based on a misunderstanding. The ProEstimates crowd are saying “What is wrong with estimates? It is just a simple tool to help teams plan how much work to take on each sprint”. The NoEstimates crowd are saying “if you are making promises to customers, and trying to price your work, there are much more professional ways to do it than guessing”. The ProEstimates crowd just don’t see things like offers, contracts and pricing to be relevant. Heck the Scrum Guide doesn’t even mention them. All that businessy stuff happens way upstream anyway so we just have to accept whatever deal management outside the Scrum team has made, and as long as we carry out the work according to Scrum we are all agile right?

I agree with both sides, which is possible because they are talking about completely different things. I just find the ProEstimate argument to be boring, obvious, non-controversial and not addressing any particular problem. The NoEstimate argument on the other hand is advocating one of the critical next steps that the software development community needs to take in order to restore a culture suitable for software development and good faith with our customers.

The other misunderstanding I see in the NoEstimates debate is that the ProEstimates crowd thinks the NoEstimates advocates are somehow refusing to answer questions like “How much does it cost?” and “How long will it take?”. This is quite false. As far as I am aware the NoEstimates crowd are attempting to answer exactly these questions using techniques with a higher level of professionalism and more reliability than guessing.

Anyway the opinions I have on pricing are based on experience, and they are also more relevant to some contexts than others. I believe this blog post is highly relevant to the following types of software development, which is where I have most experience:

  • Companies doing custom software development work for other companies.
  • Product companies where the customers pay for the features they want and even the bugs they want fixed.

I suspect this blog post might be less relevant for the following types of software development:

  • Internal IT. I have little experience in this area, and even less in how it is priced and funded, but I suspect things are a lot simpler than when dealing with an external customer
  • Product companies where the product is funded in another way separate to the development of features. E.g. via a subscription model, or advertising, or purchases of new versions. I do have a bit of experience in this area, and things are a lot simpler.

I think a lot of people on the ProEstimates side of the fence are engaged in the latter areas and simply don’t see the issues that the NoEstimates guys are having to deal with.

There is also a grey area in-between, such as where are large company has outsourced its IT and while the company doing the software development is technically doing custom development for a customer things are also much simpler as there is only one customer. In effect it is basically the same as internal IT.

So what is the problem?

I have worked for a number of companies in the former category that used similar methods for pricing software and suffered similar disadvantages because of it. Generally these companies rely on a horrendous mix of time tracking, rate cards, up front estimation in person-days, time & materials billing, bookable time and “slack” divided up according to percentages, and the need to explain to customers why the actual amount billed differed slightly from its up-front estimate. For me this is the worst. And so many of these customers are using agile approaches like Scrum to develop the software too. You would think they would be aware of the dangers of things like time tracking. The community (with the exception of Scott Ambler) seem to be unanimously against it. But unfortunately those with an understanding of knowledge work and product development are not those making the deals. They are usually a very different type of person unlikely to read books like Don Reinersten’s Flow, or engage in the subtleties of the economics of software development at conferences or online. They are more like the software equivalent of the used car salesman. 

So here is how it works: the customer has an idea of what they want. Sometimes this is just a vision (which is good), sometimes it is a more detailed list of requirements (which is ok, but a little bit wasteful as it is highly likely to change). The salesman will then take some of the team capacity and if the customer only had a vision those team members will then have to come up with some business and technical concept and estimate how many person-hours of each role is required to develop each bit of the solution. If the customer presented a more detailed list of requirements then they can skip the business concept, and just come up with the technical concept and an estimate. The salesman has to choose carefully how many and which team members get to be a part of the conception and estimation activity. You don’t want the whole team as this is all non-bookable time, which is perceived by such cultures as expensive, so usually the salesman picks the architect, the analyst and the best senior developer, or something like that.

This approach is already non-agile, or worse than that, it is fundamentally against the realities of knowledge work and product development, regardless of “agile”:

  • The idea of having a complete set of requirements at the beginning is long known to be unrealistic, the the downsides to this way of thinking are well known. Many of the requirements will, according to the Pareto Principle, be superfluous in the sense that their effort in being developed will be out of proportion to their use in the finished product. It is also a myth that anyone can know in advance what is required, This always changes. The customer never gets exactly what they want, and even before they see the first version they change their mind about what they think they require.
  • It is actually preferred, and more realistic to start with a mere vision. This allows the true scope to be discovered, adjust and grow as the development endeavour proceeds, and starts off with the knowledge that scope is and should be negotiable. The idea of having a complete set of requirements works against this. For the actual software company to start with something good (a vision) and discard all the advantages by turning that into a detailed list of requirements up front is bizarre and ridiculous. The chances of it being what is actually best for the customer are even less than if the customer themselves came up with a list.
  • It is also pretty disadvantageous to select a sub-set of the team to create the conceptions and estimates. This requires crossing the problem-solution line, and breaks one of the rules of estimation that it has to be done by the whole team. In software development, the team should be problem solvers. They should get an idea of something small that the customer desires, and work with the customer in solving the problem, implementing the solution as software and realising it as true customer value. With the used-car-salesman approach, the small sub-team of elites are trusted with the task of solving the problem, and determining the solution up-front, and the actual development team are reduced to mere source code typists, which is highly demotivating.
  • Additionally the estimates are usually much more optimistic than if they had been given by the team, and those in the sub-team are not available to the development team for assisting with the actual development of actual software.
  • It is also a waste of time, all these discussion that take place during conception and estimation still need to be held again so the actual whole team can understand them. (At least this second discussion might be bookable to the customer).
  • If you are using something like Scrum, combined with estimation in story points which is fairly typical, you have to go through and estimate everything again anyway.
  • Also these estimates are usually “ideal”. They only reflect the actual minimal time an expert might spend on typing in the solution once and that is all. Anything like research, or learning, or pair programming, or communicating with each other, or improving the system, or tests, or refactoring is extra. That is why project managers add a buffer to to the estimates or the price that the customer sees, so they have some wiggle room later, but the actual team still sees the tighter estimates. After all if you let them see the actual buffered values they will simply chew the buffer up with non-value-adding activities like refactoring or writing tests, and there won’t be any buffer left at the end to make up for the shortfall which for some reason always occurs at the end.

So what happens next? The developers start counting hours present in the workplace and recording them in some electronic system. This is called time-tracking, and suffers the following problems:

  • Some people say the main or only problem is the time that time-tracking takes. This might be the most obvious issue but it is the least of it. Sure it can chew up around 15 minutes per day, but time tracking is much more evil than that.
  • The developers have a budget per feature, and there is a general hectic vibe with everyone primarily concerned with which booking position every minute of the day belongs to. No one want’s to be the guy that has less bookable hours than anyone else. In fact everyone tries to keep their bookable hours as close to 100 percent as possible, as the general perception is that any hour not booked is wasted. Typically project managers and even product owners insist that anything like knowledge transfer, or writing tests, or refactoring or even one person in a programming pair shouldn’t be at the customer’s cost, and has to be booked to an internal booking position. As a result, these activities simply do not get done, or at least no one wants to spend much time on them.
  • The teams more expensive roles end up siting there idle. Since the project manager was involved in the technical conception and estimation, and was concerned with presenting as low a cost as possible to the customer, he preferred to see more (cheaper) junior developer hours being offered as more expensive architect or senior developer hours. As a result, even when the team is struggling to meet its sprint goals, the architects sit there doing nothing because if he did the work the customer would get a more expensive bill than if the junior developer did it. The customer would then come back and demand to know why he was charged architect costs for something that could have been done by a junior developer. As a result project managers insist on architects NOT helping the team to meet their sprint goals, which damages the feeling of trust in the team.
  • A related issue is when cheaper developers get assigned the tasks where there is a high risk of requiring more time than that estimated. I have seen a team suffer a huge drop in motivation when a student, with a cheap per hour rate, was given all the most interesting tasks (that were sold to the customer as junior or senior developer hours), because he essentially had more than twice as much time as estimated to do it, and you automatically have some extra buffer for the risky, more innovative and interesting parts of the “project”.

I hear a lot of managers claim that time & materials works well for them, and that estimates correspond very well with actual development hours. That is because developers are painfully aware of their budget, and compromise on quality in order not to “overspend” their time budget. Without fail these managers also wonder why they run into technical debt issues a year later. Actually they don’t wonder. They know it is down to poor commitment and discipline on the part of the developers. On the other side of that coin is that it discourages innovation, and encourages maximising expended effort. Assume a task was estimated at 5 days. If someone can find a clever way to do it in 2 days he probably should right? Well with T&M there is no incentive. If he does it in 2, then he might not have anything else to do for the week and his bookable hours will drop. Also the company will  get 3 days worth of money less. Usually project managers solve this by shuffling hours around and lying to the customer about what took how long. They will simply say it took 5 days, and use the extra 3 days to reduce something that took longer than expected.

Particularly sad are the companies that think they are cool and generous like google for allocating a 20% “slack” time that doesn’t have to be bookable. This implies that everyone is under extreme pressure to book the other 80% of their time. Guess what ends up being done in the 20%? Meetings, bug fixes that the product owner thinks should not be billed to the customer, writing tests, learning from other developers, pair programming and refactoring. It is much better NOT to have such a percentage goal of bookable hours. The team needs the freedom to decide for themselves how to best to allocate their time in order to deliver, and besides, the customer pays for everything anyway. It is not like the government pays for the 20% time. This trick might look good at first glance, but it is total bullshit that has no pros, and only cons.

There is one general issue that lies at the root cause of all the parts of this nasty approach to pricing software development efforts: The idea that it is appropriate to measure software in terms of person-hours. Once we get beyond that dangerous myth, we instantly solve a number of problems and we open things up to the next level of professionalism in managing software development.

So what is the alternative?

So let’s look at better models for pricing software in order from best to worst, according to my opinion:

  1. Value based pricing: The best way to price software is according to the value it brings the customer. We can negotiate with the customer and help him discover what sort of value the delivered software might bring, and come up with a price that correlates with the expected level of investment required to bring such a return. However I find this suffers from a couple of problems that might make this approach difficult:
    • Business value is hard to determine. Software development, when worthwhile, is a high risk endeavour, featuring an asymmetric payoff function similar to the development of medications. We can expect to start a large number of experiments with the hope that they will be highly successful, and expect that most of them will be canceled as soon as we discover that they are not going to be a big winner. The occasional big winner results in so much profit that it more than covers the losses associated with the “failed” experiments. (Actually, the information we learn from these experiments usually makes the investment worthwhile, so failure is probably mot the right word). The fact is, we often have to at least start the development process and test a feature or two on the market before we even know what its value might be. This is hard enough at the project level, and even harder at the “story” level that agile development prefers, so I suspect for this reason value based pricing to be very difficult in practice. One model that could work would be to measure actual value afterwards, but this requires a high level of trust, and exposes extra risks for all participants. It essentially makes the software development company a full stakeholder in the product, which may or may not make business sense.
    • The other issue is that customers may not be willing to share their expected value, even if they know it.  They want to get the lowest price possible, and not give the software vendor a hint as to the maximum they might pay. There are also a lot of things that can be done cheaply and easily, but result in huge wins for the customer. The vendor might think it is fair to take the usual percentage cut of the wins, but the customer most likely does not.
    • Even if we know the customer value, before we decide if we should do it or not we might like to know to what degree, if at all, it covers our costs. This means that even when using value based pricing, we might still have to use one of the following more cost-based methods to determine if we should do it or not.
  2. Price per feature (determined at time of commitment): My current favourite model is very simple and based on measuring the teams price per (average) groomed feature. It works especially well with a system where Kanban plays a role. You should have a rough idea of your costs. Ideally they are mostly a function of team salaries and fairly fixed, otherwise in more dynamic environments you can determine separate components, perhaps basing it partially on an average of previous months, and known costs for the next month. You simply divide these costs by the throughput and add an appropriate margin. Before the customer and team commit together to developing a feature, some backlog grooming should occur and the team should perform the usual steps of story splitting. Queue replenishment consists of presenting the split stories to the customer, together with the current price per feature. They can select as many stories as there are free places in the input queue. When working with multiple customers it is good to authorise the product owners to do this on behalf of the customer, or to establish some idea of how much team capacity is to be allocated to each customer (ideally in terms of total system WIP). This shouldn’t be too big a deal, the PO can communicate with the customer up until queue replenishment about what the price could be and how many free slots the customer will have. The price is fixed at the time of moving the item from the backlog to the input queue, and payment is due a number of days after the item is done. If you have a two stage commitment system, or end up cancelling more than a handful of items in the middle of the process and have multiple customers then it could get a little more complicated, but I might blog separately about that. I don’t currently see any disadvantages, but I know someone will have some questions about it so please challenge me in the comments, and allow me the opportunity to make this concept even more solid. I know a lot of people seem to think it will only work with items that are “roughly the same size”. This is not true, and in fact the concept of size is a bit bogus when considering the whole value stream. We groom and split in order to preserve some liquidity and flow in the process, to prevent large items from blocking the system, and to inhibit the lead time distribution from blowing out too far to the right. I fully expect significant differences in the measured lead times of different items, that is the reality of knowledge work and product development, but there is no real need why they all need different prices. If the customer has 3 features in the backlog, but only feels 2 are offer enough value to justify the price per feature, then he should only choose those 2.
  3. Renting team capacity for a period of time (in terms of system WIP, not in available person-hours): This might be an ok option for those doing a longer term software development effort, and wan’t to save the communication overheads of accepting a small offer every week or so. It is also based on a Kanban approach. Assuming costs (plus margin) of 100,000 per month, and a total system WIP limit of 100, then we could have one customer paying 30,000 per month for exclusive rights to 30 of that WIP, and so on. If the throughput is 100 items per month, we might expect he gets to see 30 items per month. Or he might not. We could provide both options and allow him to choose which is best for him.
  4. Fixed price per team-day or team-sprint (aka. T&M light): This is probably good for Scrum teams, or teams when you only have a single customer and don’t have too many issues with balancing capacity between different customers or classes of service. It is also based on costs plus margin. One discussion I got into recently on twitter was with a defender of T&M. It turns out they don’t do up-front estimates of entire projects, they don’t have rate cards, they don’t have a target number of billable hours and most importantly they don’t do time tracking. Basically for every day a team works, they get a bill for a team day with a discount for team members on holiday. To me this is a lot closer to a fixed price per team-day than the true T&M monster as typically practiced. However they reported it requires a large amount of trust, and only works when the team has a single customer (which some consider ideal, but I personally consider it a risk of the “all eggs in one basket” variety.) The team just developers iteration after iteration until either the product is good enough, or the customer decides they have spent enough money.
  5. Fixed price variable scope: This is the classic agile fixed price scenario where there is some budget set up in advance, and the team simply develops iteration after iteration until the money runs out. It is essentially equivalent to the fixed-price per sprint, except presumably the option to quit before the fixed budget runs out is excluded. I don’t know what is supposed to happen if the product is good enough before the budget runs out. I guess the team is supposed to keep developing unwanted features until the budget runs out. There is also the question of how is this budget determined. I guess the customer has some idea of what he wants to spend. I could also imagine it being based on a rough release plan, which is in turn based on an initial but negotiable backlog and a known velocity. I am not sure what advantages this model brings over the previously mentioned ones.
  6. Fixed price, fixed scope, but the price is obviously sufficient to cover costs and the scope is easily achievable by the due date: Sometimes we get lucky even with dysfunctional traditional methods. As long as we ask for more than enough money to cover things even if things go wrong, and we leave ourselves plenty of time to get things done, even with the inevitable changes in scope, then why not? It is still better than the full-on T&M model with all its disadvantages. But not much better.
  7. Fixed price, fixed scope, fixed due date, and the team thinks it will be tight: This might even be worse than full-on T&M. I don’t know which one is worse. They are both extremely damaging. Sadly they are the 2 most common approaches. In fact the typical Scrum-using but otherwise not very agile company thinks they are the only two options. They are convinced that one of them is not “agile” so the other one must be. Usually a company has a bad experience with number 7 so declares it un-agile, and then feels super smug and ultra-agile for using full-on T&M together with Scrum.

So there you have it. My current views on the various approaches to the pricing of software development. I have to mention again that my favourite is 2. I don’t really have a problem with any of 1-4. I don’t see much point in 5. 6, 7, and the full-on T&M I described at the beginning are the used-car salesman approaches. They are lazy, damaging, unprofessional and betray a poor understanding of how knowledge work and product development works. Instead of violating our customers and teams with such approaches we need to think about things a bit deeper, and consider the damage we are doing, and start behaving more like professionals. The relationship between the software development and the customer is too important to be left to sales-people. It requires product developers to be involved. It needs to be more like the way a doctor and their patient communicate, than the way we currently operate, as if it were possible to fix scope and sell person-hours like the kids at McDonalds sell fries.

I recently read a blog post from someone, it isn’t that great, it exhibits one of the misunderstandings about NoEstimates (he somehow thinks NoEstimates is all about refusing to answer the “how much” or the “how long” questions), but one quote was interesting:

If you don’t know where you are going, if you don’t have some notion of what done looks like, if you can’t tell me approximately how much and how long, please don’t start.

At first I thought, woah wait a minute, this pretty much excludes anything in the complex domain, aka anything worth while. Even beginner agilists know that software development is an experimental process, and it is quite typical to begin something before we know how much it will end up costing, or how long it will take. But on second thought I agree with him. There is no way to know what done looks like when we are talking about a large project, no way of knowing how much it should cost, and no way to know how long it will take. They can only ever be discovered once we have invested some effort in the information generation aka software development process. So I agree. We should not do large projects. However we do know what done looks like at the story level. We can say how much it will cost, and we can provide a certain degree of confidence about how long a story will take based on concrete measurements and backed up by statistics. So I agree. We should only ever do story sized things. Actually why not take his quote even more seriously and use it to base our definition of what we should attempt to develop? If we don’t know what done looks like, we can’t put a price on it, and we can’t say how long it will take then we shouldn’t start it. It is obvious what he means. We shouldn’t do anything larger than stories, we have to get away from projects being the main batch size of relevance to pricing, offers and customer communication in general.

So here are the main points again:

  • Don’t sell person-hours, it is not appropriate for things like software
  • Don’t pretend scope can be fixed in advanced
  • Don’t use time tracking
  • Don’t use T&M billing
  • Only estimate where and how it is appropriate, the whole team may use story points to plan how much work to take on per sprint, and that is pretty much the only place for estimation in software development.
  • Never estimate in hours, only relative units like points
  • Never base prices on estimates, use measurements instead
  • If you have customer contact, write offers, work out prices or negotiate contracts, please go to a couple of conferences, read a book or two, and engage with the community
  • Don’t think you are cool by gifting your employees 20% slack time (by insisting 80% of hours must be bookable), all you end up doing is pressuring the employees not to spend time doing what they should. And it really messes with the idea that a team should self-organise
  • If the offer and pricing is fundamentally not “agile” or at least makes no sense from a knowledge work and product development perspective, then planning the development using Scrum won’t help you much
  • Forget about “projects”. When it comes to prices and offers, we don’t want to deal with anything larger than a story

I have a feeling this might be a blog post I keep coming back to and refining. I already suspect I have left some interesting details out.

Any questions or comments? 

Addendum 1: Two additional models that I have been made aware of but forgot to include to this list are the “price per story point” model. I don’t prefer it, as it suffers from many of the same disadvantages that other approaches based on up-front estimation suffer, but if you are estimating in story points anyway, it might work for you. I would probably put it somewhere between 4 and 5 maybe. The other model is the incremental funding method. This is a really great one if you can get it to work. In this method we minimise initial investment and risk, and focus on developing a product that makes sufficient money to fund further development. This concept isn’t really an alternative pricing model as such, and can thus be combined with any of the above listed pricing models as an additional technique. You could even use it to filter out projects that should not be invested in past their initial MVP. Any projects that don’t self fund after a calculable investment in money or time should be cancelled, so that that investment can be channeled in more worthwhile activities. I believe Don Reinertsen’s book Flow even presents some useful numbers that can be used to help support such decisions in the section on asymmetric payoff functions.

6 Comments »

  1. This is a great post. We work in a software intensive world of space flight, aircraft, and other embedded, flight, and ground systems.
    I’d like to suggest that the very first thing to be done is to banish the word “guessing” as a synonym for “estimate.” That is the furthest from the factual approach for “professional; estimating.” There are several profession organizing for “estimating.” https://www.iceaaonline.org/ and http://www.aacei.org/ are two, plus a hald dozen or so tools we use for estimating.

    None of the outcomes from these processes are guesses. I sense the #NoEstimates folks consider estimates as “guesses,” but that’s a non-starter where we come from. Each agency (NASA/DOD/DOE) and firm that contracts with them has a “cost estimating” department and we are mandated to produce a probabilistic (Monte Carlo Simulation) of the cost, schedule, and technical performance estimate at completion every month as a submittal to the customer.

    This reminds me of the push back from the traditional software development community when agile came, but in reverse.

    Again, great post, I’m forwarding it to the members of or GAO Cost and Scheduling Committee and the NDIA (National Defense Industry Association) program controls committee which is now integrating agile to our Earned Value Management process guide.

    Comment by Glen B. Alleman — May 21, 2013 @ 03:19

  2. Great blog post!

    I think as well that option 2 (Price per feature) is the best one… However, seems as is very hard to apply in practice, during deal negotiations. Client wants the main feature – but that main feature is “project” on some kind – to achieve that goal, there are a lot smaller features what must be implemented before the main one… for what client is not happy to “pay” – because of that small “feature” alone – worth nothing…i.e. Let say “Invoicing” is main feature… to achieve that we need at least:

    -Customers
    -Items
    -Taxes
    etc

    to “buy” and use each feature alone or all together (before “Invoicing”) – worth nothing…

    So, I think what works is some kind of mixture 2 and 3… Price the main future, then divide on smaller period/payments (to achieve the main goal – that team capacity will be “rented” on some kind for the period), and of course in the pricing the feature we need to calculate and collaboration time before start coding (collaboration will continue and during coding, but it is important, before start to get “clearer” picture about full process to achieve the main goal), and testing time…

    Cheers,

    Misa

    Comment by Misa Simic (@MisaSimic) — June 20, 2013 @ 11:37

  3. Hi Kurt,

    interesting article. In the section about “Price per Feature” you said:

    “Before the customer and team commit together to developing a feature, some backlog grooming should occur and the team should perform the usual steps of story splitting.”

    Do you mind elaborating, or provide links to earlier blog posts, what you understand by “backlog grooming” and “story splitting”? What’s the aim of those activities for you? Who participates? How small should stories be split?

    I think this is crucial to understand how you imagine Price per Feature to work.

    Thanks for Your thougts,
    Andreas Ebbert-Karroum

    Comment by Andreas Ebbert-Karroum — September 11, 2013 @ 14:50

  4. The details would be context dependent I guess, but I think what people do now days and call backlog grooming or refinement should be appropriate and probably necessary for price per feature. I will explain what I mean, but I don’t want to be dogmatic about it, if someone else does something different it is probably fine. I don’t think anything is new here but just for the sake of understanding I will explain how I see it.

    Backlog refinement is the activity, or maybe a series of activities, engaged in in order to get an item ready for the development team. I have always considered three aspects: Splitting the items so they wont take too long (i.e. for a Scrum sprint), specifying the acceptance criteria, and providing an estimate.

    I no longer consider estimates important however. Also unmentioned but might be important is that while performing these activities the team discusses and learns about the items. That might be a nice side effect but I don’t consider it the core function of backlog refinement.

    In Scrum this generally all happens while the items are in the product backlog. In some of the Scrumban and flow-based approaches I have worked with where Kanban was being used, there were sometimes specific columns after the backlog where these activities occur. I have also seen non-standard approaches such as expand/collapse, and the idea of “extracting” stories from an epic over time rather than splitting it completely in one sitting. Story splitting is the activity of taking an epic or large story, and splitting it into more atomic stories (that still have meaning for the customer) in one go. There are a few checklists and cheat sheets available that list potential ways we can do this. e.g. looking for words like and or or, splitting a story into workflow steps (which may break the INVEST criteria..), or making a new story out of each of the acceptance criteria.

    I think both making sure the items go through a splitting AND ensuring acceptance criteria is especially important when pricing per feature as we want to avoid the risk of treating larger and larger packets of items being treated as single items, and we need clear acceptance criteria to avoid arguments about whether we have delivered what is expected or not.

    Who participates? Depends, I tend to prefer involving the whole team, but I can imagine situations where a subset of the team or even an individual do it. How “small” should they be split? Well I would not be able to put a number on it, and wouldn’t try to. I know some people do however. My approach would be to look at the story splitting checklist and see if it is possible to split the item more than it already is while still having customer meaning. But other approaches are fine too. The reality is they will all have different “sizes” or at least all have different lead times through the system, and different levels of impact on the throughput, but the nature of that variability is best handled, in my opinion, by measuring it and understanding its distribution rather than trying to e.g. set a target or maximum size that every story must conform to.

    I hope that clarifies it a bit. I tried to get the point across that I don’t find it useful to prescribe a dogmatic best way to do it, merely to mention that it might be necessary to do some form of refinement before presenting the items to the customer for final approval/commitment to begin development.

    Please ask if you have any more questions.

    Comment by Kurt Häusler — September 11, 2013 @ 15:42

  5. Hi Kurt,

    a good post with an interesting topic to discuss.

    As customer in the “price per feature” model I see the problem to get a rough idea about the cost of a bigger idea I have. The idea have to be split in features to get a reasonably accurate calculation of the costs (and the needed time to get it). So there is a not negligible amount of analyzing effort to do upfront.

    In my experience all sponsors of software development need to do some kind of cost-effectiveness considerations. Therefor they need some numbers about the expected costs. In the “price per feature” a estimation of the amount of features, in the “fix-price per team-sprint” the amount of team sprint or in the “renting team capacity for a period of time” the amount of periods of time. Non of the discussed pricing models will help you in that question.

    Thanks,

    Marc Clemens

    Comment by Marc Clemens — October 9, 2013 @ 16:40

  6. Hi Marc, Yep you are right, they are totally separate issues. The first paragraph though sounds like the problem with waterfall, that agile approaches solved. Instead of worrying about the price or duration of a whole project (when we don’t know anything about it), lets just worry about the price of an iteration or story or something, and decide what to do from there.

    If a customer really insists on knowing a price for a whole project in advance then that is not a problem with the price per feature model it just indicates that the customer needs a waterfall or hybrid approach and doesn’t accept a truly agile one. The price per feature model could still be used in a waterfall or hybrid project but it has the disadvantage as you mentioned of requiring a lot of “analysis” effort up front. But I should point out, it requires less effort than typical approaches. Refining a backlog of epics by splitting them into stories and then counting the stories for example is all that is required. Typical approaches still require that effort, and then go on to perform a task breakdown and estimations of the effort (in hours) that each task requires. And it has of course all the risk-disadvantages of any fixed price model so you would need to add a buffer to cover the case that your costs per feature increase after you have already negotiated the price per feature with the customer.

    I definitely had a agile approach in mind though when I wrote the post, and wasn’t really thinking of pricing more than a “story” or a “sprint” at a time, i.e. making the pricing and offering parts of the process within the agile iteration rather than in a waterfall style “phase” at the beginning.

    However in “price per feature” I don’t think the software provider should be estimating the number of features in the in the whole project, any more than a Scrum team should tell the customer how many items will ever be in the backlog! Now I haven’t thought about how this might look in a waterfall or hybrid project, but in an agile project it should just pretty much the same as Scrum. There is some backlog of epics than needs to be refined and at least partially split into stories, and then we have something to work with. It is not like the customer comes to the team and says “I want a web shop” and the team says “ok, that will be 1142 PBIs”. The customer essentially determines how many features he wants, and the team can then use that as input to base a price.

    The number of team sprints is essentially release planning in scrum right? This is not done once up front but continually through the project, as prices should be. Anyone already working with agile should be used to not getting a fixed release date up front, the idea that prices are just as hard to fix up front shouldn’t be that hard.

    So you are right, these pricing models don’t help that particular issue, but that is ok. Other approaches such as agile itself, and more specifically things like Scrum release planning already provide possible solutions, and the pricing models are compatible with them.